Shift Handover Sheet and Tool for CNC Shops
Fill in one card per machine on your phone or tablet during the last hour of the shift. Then print the A4 sheet, save it as a PDF, or send it on WhatsApp to the next shift. It asks for what generic checklists miss: the program and where it stopped, offsets and tools changed, the last measured value, and any temporary measure. Everything runs in your browser: nothing you type is sent to us.
Why handovers fail, and how to run one in five minutes: Shift Handover Checklist for a CNC Shop.
Your handover
Fill in a machine card and your handover appears here, ready to print or send.
This handover is long, so WhatsApp will copy it for you to paste instead of typing it in.
WhatsApp opens with the message typed in, and you choose who gets it. It is not sent to us. Prints on one A4 landscape page with signature boxes.
The WhatsApp message
See the whole message
How to use it on the shop floor
1. Fill it during the shift
Each operator keeps the line for their own machine as a job starts, changes or stops. They can fill their own card here and press "Send on WhatsApp" under it, or write it on the printed sheet. In the last 30 to 45 minutes the supervisor walks the machines, checks each line against the machine, and adds it here. The tool marks any line that still needs something, such as done, left and rejected, or the last measured value.
2. Say it and show it
Outgoing and incoming operators talk through each machine's line at the machine. Then the two supervisors walk the machines with the printed sheet or the phone: the outgoing one talks, the incoming one asks and checks. Written alone, it gets skimmed. Spoken alone, it is forgotten by evening.
3. Send it, sign it, read it
Send the message to the incoming supervisor or the shift group, print the sheet for signatures, and read it the next morning. Blocked items get a name and a time, and the owner sees the record.
One handover per shift, on one phone. Your entries are kept on the device you use, so the supervisor's phone or tablet holds the handover. An operator can fill just their own machine's card on their own phone and press Send on WhatsApp under it: the supervisor taps the link, and the tool offers to add that line. The line travels inside the link and is not sent to us. Sending one line is a one-way hand-off. The tool does not update live, keep a history or show who has not sent theirs yet. Operators can also use the printed sheet, which the supervisor checks at the machine and enters here.
Prefer paper only? Download the blank one-page PDF to fill in by hand. For why handovers fail and what each line is for, read Shift Handover Checklist for a CNC Shop.
What a filled-in machine line looks like
This is one machine line as the next shift should receive it. The job, numbers and names are made up for the example. Compare it with the usual handover, "VMC 4 running, job 2217, ok", which tells the next shift almost nothing.
VMC 4
Example only
- Job
- 2217, op 20, rev C
- Done / left / rejected
- 90 / 110 / 2
- Program
- O1234, stopped at N120, between cycles
- Changes made
- Offset changed: X offset on T4 +0.03 after piece 90
- Quality
- Bore 25.012 at 1:40 PM, limit 25.015. Near the limit, rejects found
- Temporary measure
- T4 offset hand-adjusted +0.03, approved by Suresh. Program to be corrected tomorrow, then the adjustment is removed
- Blocked or waiting
- Material: purchase chasing bar, promised by 6 PM
- Next job
- 2218, op 10. Not ready: bar not in
- Machine condition
- Spindle noise at high rpm
What each part of the line is for
Every part answers a question the next shift would otherwise have to ask, or find out the hard way.
| Part of the line | The question it answers |
|---|---|
| Job, operation, revision | Which job is on the machine, and which drawing revision is it running to? |
| Done, left, rejected | How far along is it, and is the count still correct? "Running" does not say. |
| Program and where it stopped | Where do I restart, and is it safe to restart there? |
| Changes made | What was changed that the drawing and the job card do not show: an offset, an insert, an edited program? |
| Quality: last measured value | How close is the critical size to its limit, and when was it last checked? |
| Temporary measure | Is a workaround in force, who approved it, and what has to happen before it is removed? |
| Blocked or waiting | What is stuck, and who is chasing it, by when? |
| Next job and readiness | What runs after this, and are the material, program, tools and fixture ready? |
| Machine condition | Is anything abnormal, such as an alarm, noise, low coolant or a maintenance need? |
On top of the machine lines, the whole-shop block carries priority changes, machines down, material or outside work due, staff cover, and the one thing the next shift must watch. The reasoning behind each line is in Shift Handover Checklist for a CNC Shop.
Paper sheet, spreadsheet or this tool?
Any of the three works if the supervisor checks each line at the machine. They differ in how much help you get while filling it in, and in what each one cannot do.
| Printed sheet | Spreadsheet | This tool | |
|---|---|---|---|
| Works at the machine | Yes, on a clipboard | Awkward on a phone | Yes, phone first |
| Flags a line that only says "running" | No | Only if someone builds the check | Yes, line by line |
| Reaches the next shift | Handed over on paper | Shared file or email | WhatsApp message, or print the A4 sheet |
| Signatures | Yes | After printing | On the printed sheet |
| Several people fill it at once | One row each, on one sheet | Yes, on a shared file | Each person can send their own line to the supervisor's phone by WhatsApp. One phone holds the handover, with no live view |
| Where your entries are kept | On paper | In the file | On your device only, never sent to us |
The tool's limit is real: it holds one handover on one phone. Operators can send their own line to that phone, or you can give them the printed sheet for the supervisor to check and enter. What it cannot do is show everyone's lines live, keep a history, or tell the owner what is blocked without someone passing a message. That needs a shared record, and it is what our Operational Workflow Review looks at.
Common questions
What should a CNC shift handover include?
For each machine: the job, operation and revision; how many pieces are done, left and rejected; the program and where it stopped; any offset, tool, insert or fixture change; the last measured value on the critical size; any temporary measure in force, who approved it and what ends it; what is blocked and who is chasing it; and the next job with whether it is ready. For the whole shop: priority changes, machines down, material or outside work due, and the one thing the next shift must watch. Shift Handover Checklist for a CNC Shop.
Who fills in the shift handover: the operator or the supervisor?
Both, in different roles. Each operator keeps the line for their own machine during the shift. In the last 30 to 45 minutes the outgoing supervisor walks the machines, checks every line against the machine, completes the whole-shop block and signs. The incoming supervisor reads it, walks the machines, asks questions and takes the shift. There is one handover per shift, and it stays with the supervisors. In this tool, the supervisor's phone or tablet holds it. An operator who wants to write their own line can fill just their machine's card on their own phone and press "Send on WhatsApp"; the supervisor taps the link and the tool adds that line to the handover. Shift Handover Checklist for a CNC Shop.
Is anything I type saved or sent to you?
No. The tool runs in your browser. We only count that it was used: that a handover was filled in, printed or shared, with no names, jobs or numbers. What you type is kept on your own device only, so a lost signal or a refresh doesn't lose your work; when you come back you can open it or start fresh, and Start fresh clears it. When you send it on WhatsApp, it goes from your phone to the person you choose, not through us. The same is true when an operator sends one machine line to the supervisor: the line travels inside the link, and the link is read by the person who opens it, not by our server. On a shared phone or computer, press Start fresh when you finish.
How does the next shift get the handover?
Three ways. Send it on WhatsApp to the incoming supervisor or the shift group: the message is typed in for you. Print the A4 sheet, or save it as a PDF, and read it together at the machines. Or do both. The best handover is spoken at the machine over the sheet, so use the message as the record, not as a replacement for the walk.
Why does the tool say my line needs fixing when I wrote "running"?
"Running" tells the next shift nothing: which job, how many are done, where the program stopped. The tool asks for done, left and rejected, the changes made and the last measured value. You can still send it as it is, but those are the lines where information gets lost.
Does it work on a phone or tablet on the shop floor?
Yes. It is built for a phone first: one card per machine, large tap buttons for the common answers, and numbers on a numeric keypad. Open it in your phone browser. Your handover stays on that phone, so use the same phone for the whole handover.