Free tool

Bottleneck Finder for CNC Job Shops

A bottleneck is the step that limits how much your whole shop can ship. In a job shop it is rarely the machine everyone points at. Enter your machines and the steps between them, and the tool runs the five checks from our guide: load against available hours, the queue in front of each step, where your late jobs waited, which steps stand idle for want of work, and what people wait for. It names the likely bottleneck. Everything runs in your browser: nothing you type is sent to us.

The method behind it, with a worked example: How to Identify Bottlenecks in Manufacturing.

Step 1: Your machines and the steps between them

Add every machine, and the steps jobs wait for. Use hours for the next one to two weeks, the same period for each. Jobs waiting is the average on the morning walk. Late jobs is how many of your last ten late jobs waited longest here. Fill in what you know; leave the rest empty. Saved on this device as you type, never sent to us.

Step 2: Your guess (optional)

Which step do you think is the bottleneck? We will tell you if the numbers agree.

Finished? Clear all entries from this device.

The five checks, and what counts as a hit

No single check is reliable on its own in a job shop. A step that shows up in three or more of them is a probable bottleneck; in two, a possible one.

  1. 1. Queue

    You enter
    Jobs waiting in front of it on an average morning
    A step is a hit when
    Its queue is at least 3 jobs and within a quarter of the longest queue
  2. 2. Load

    You enter
    Hours of work planned, and hours available
    A step is a hit when
    Planned hours are 95% or more of available hours
  3. 3. Late jobs

    You enter
    How many of your last ten late jobs waited longest here
    A step is a hit when
    At least 2 jobs, and at least 40% of all late jobs entered
  4. 4. Idle steps

    You enter
    Which steps stand idle for want of work, and which step feeds them
    A step is a hit when
    It is the step feeding an idle step
  5. 5. What people wait for

    You enter
    Tick the steps operators say they wait for
    A step is a hit when
    It is ticked

These limits are rules of thumb, not a standard. The tool does not know your shop: it shows where your own numbers point. The reasoning, a worked example and what to do once you have found it are in How to Identify Bottlenecks in Manufacturing. Prefer paper? Print the one-page Bottleneck Check Sheet and fill it in on the floor. A tool sees only what you tell it, and only today. Keeping the queue and load at the bottleneck visible every day, as work moves, is what our Operational Workflow Review looks at.

Common questions

What is a bottleneck in manufacturing?

A bottleneck is the step in production with the least capacity compared with the work it receives, so it limits how much the whole shop can ship. In a CNC job shop it is not always a machine: it can be the one programmer, the setter everyone waits for, first-off approval, the CMM, or an outside process such as heat treatment or plating. An hour lost at the bottleneck is an hour lost for the whole shop. How to Identify Bottlenecks in Manufacturing.

How do you calculate a bottleneck?

For each machine or step, divide the hours of work planned for the next one to two weeks (setup plus run time) by the hours really available in that period, then multiply by 100. The step at or above about 95% to 100% is a constraint, and the one with the highest figure is the first suspect. Load alone can mislead in a job shop, so this tool also looks at the queue in front of each step, where your late jobs waited, which steps stand idle for want of work, and what people say they wait for. How to Identify Bottlenecks in Manufacturing.

What are the two types of bottlenecks?

A short-term bottleneck is temporary: a machine breakdown, one rush job, an absent programmer. A long-term bottleneck is permanent: the step simply has less capacity than the work arriving at it, week after week. In a high-mix job shop the bottleneck also moves with the job mix, so a long-term one can shift when a new customer or part family arrives. How to Identify Bottlenecks in Manufacturing.

Is the busiest machine always the bottleneck?

No. A machine can run all day on long jobs and still have spare hours for what is due, while a machine at lower utilization has a week of work queued in front of it. Utilization shows how busy a machine is. A bottleneck is about load against available hours, and about where work waits. The tool has a "Your guess" box so you can compare what you believed with what your numbers say. Why Machine Utilization Numbers Are Lying to You.

Why does the tool give me a "possible" and not a "probable" bottleneck?

A step is marked probable when it shows up in three or more of the five checks, and possible when it shows up in two. With only the hours filled in, no step can reach three. Add the queue in front of each step, tick the steps people say they wait for, and enter where your last late jobs waited, and the answer firms up.

Is anything I type saved or sent to you?

No. The tool runs in your browser. We only count that it was used: that a result was shown, printed or shared, with no step names or numbers. What you type is kept on your own device only, so a refresh does not lose your work; when you come back you can open it or start fresh, and Start fresh clears it. On a shared computer, press Start fresh when you finish.

More free tools

All free tools →

Want to see where your shop is really stuck?

The tool works from the numbers you give it. On a free 90-minute floor walk we look at how jobs actually move, where they wait, and what it would take to keep the constraint running.

Book a free floor walk